How to Avoid Construction Cost Overruns in Kenya: BQs, Contracts and Payment Milestones

By Msingi Engineering Group Updated 10 min read

A completed white family house with a paved driveway in Thome, Nairobi.

Most construction cost overruns in Kenya are not caused by one big disaster. They build up from small things: a design that was not finished, a quote that left items out, changes made on site, and payments made ahead of work. This guide explains how a bill of quantities, a clear construction contract and sensible payment milestones keep your building project on budget.

Key takeaways

  • A bill of quantities (BQ) lists every item of work with its measured quantity and price, so you can compare contractors fairly and value changes on the same rates.
  • Research on Kenyan building projects links cost overruns to material price changes, design changes, client changes to finishes, under-estimation and contractors running short of cash.
  • Building input prices can rise quickly: Kenya's construction input price index rose 5.73% in the second quarter of 2026, so your contract should say how price changes are handled.
  • Every change (variation) should be priced and approved in writing before the work is done.
  • Payment milestones should follow completed, inspected stages, with part of each payment held back as retention until defects are fixed.

Why do construction cost overruns happen in Kenya?

A University of Nairobi study of non-traditional contracts in Kenya identified the main causes of cost overruns as changes in the cost of building materials, changes in the design, changes in finishes by the client, contractors running out of money for periods of the project, and under-estimation of costs by the quantity surveyor (University of Nairobi repository).

Material and fuel prices are a real pressure. The Kenya National Bureau of Statistics (KNBS) reported that overall construction input prices rose 5.73% between the first and second quarters of 2026, with the building cost index up 5.25%, mainly because of higher transport, fuel and material costs, according to Kenyans.co.ke.

Site management matters too. In an April 2024 article in The Standard, an industry practitioner pointed to waste, theft, poor scheduling, unplanned variations and disputes as everyday drains on budgets, summing up: "Projects don't go wrong, they start wrong."

Most of these causes can be reduced before the first foundation is dug.

What is a bill of quantities, and why does it matter?

A bill of quantities (BQ) is a document that lists the measured quantities of every item shown in the drawings and specifications, such as cubic metres of concrete, square metres of walling and numbers of doors. It is usually prepared by a quantity surveyor (QS), a cost professional. Each contractor then puts a rate against every item, so every bid prices the same scope.

According to the reference site Designing Buildings, a priced BQ is used to compare tenders, agree the contract sum, value interim payments, price variations and settle the final account. That makes it one of your strongest tools against cost overruns.

In Kenya, quantity surveyors must be registered with the Board of Registration of Architects and Quantity Surveyors (BORAQS) under the Architects and Quantity Surveyors Act. NCA project registration also requires a BQ summary signed and stamped by the QS, according to Construction Kenya.

What should a good BQ include?

Section What it covers What to check
Preliminaries Site set-up, supervision, insurance, temporary water and power, security That site overheads are priced, not hidden elsewhere
Measured works Substructure, frame, walling, roofing, finishes, doors and windows That quantities match the drawings
Services (MEP) Plumbing, drainage, electrical, water storage, solar or backup power That fittings, not just pipes and cables, are included
External works Driveway, paving, boundary wall, gate, septic tank or sewer connection, landscaping Often missing from cheap quotes
Provisional sums Allowances for work not yet designed or defined Keep them small; ask how each will be firmed up
Prime cost (PC) sums Allowances for items you will choose later, such as tiles or sanitary ware That the allowance matches the finish you actually want
Contingency A reserve for the unforeseen That it is spent only with your written approval

A quote with large provisional sums or low prime cost allowances can look cheaper than it really is. When you compare contractors, check these lines first.

Which construction contract terms protect your budget?

A written construction contract turns the BQ into binding commitments. In Kenya, the Joint Building Council (JBC) conditions of contract for building works are widely used for private projects, alongside FIDIC forms (Cliffe Dekker Hofmeyr). Whatever form you use, make sure these points are covered, and have an advocate review it before you sign.

Contract term What it should say Why it protects you
Scope and documents The drawings, specifications and BQ that form the contract Defines exactly what the price buys
Contract sum and type Whether the price is a fixed lump sum or remeasured against actual quantities Tells you who carries the risk of quantities changing
Price adjustment Whether, when and how material price changes can be passed on Avoids open-ended claims when prices rise
Variations That changes must be instructed and priced in writing first Stops unapproved extras appearing on the final bill
Payment terms Stages, valuation and certification before payment Links money to work actually done
Retention The percentage held back from each payment and when it is released Gives the contractor a reason to return and fix defects
Programme and completion Start date, completion date and any agreed consequences of delay Delay costs money in rent, interest and site overheads
Defects liability period How long after completion the contractor must fix faults Protects you after you move in
Disputes How disagreements will be resolved Avoids costly delays and court action

The type of contract matters. Under the FIDIC forms used on many larger projects, the Red Book is a remeasurement contract where the employer carries the risk of estimated quantities being wrong, while the design-and-build Yellow Book is a lump-sum contract where the contractor carries the quantity risk, according to Pinsent Masons. Our comparison of design-and-build and traditional contracting explains this further.

How should payment milestones be structured?

The safest principle is simple: money follows completed, checked work. A typical sequence for a house links payments to stages such as:

  1. Mobilisation, if an advance is agreed, kept modest and tied to a signed contract.
  2. Substructure: excavation, foundations and ground floor slab complete.
  3. Superstructure: walls, columns and upper floor slabs complete.
  4. Roof: roof structure and covering complete, so the building is weather-tight.
  5. First fix: plumbing, electrical conduits and plastering complete.
  6. Finishes and second fix: floors, ceilings, joinery, fittings, painting.
  7. Practical completion and handover.
  8. Release of retention at the end of the defects liability period.

The percentage for each stage depends on the design and should be agreed in the contract. Before each payment, have the work inspected, ideally by your QS or engineer, and get a written valuation or payment certificate. Pay only into an account in the contracted company's name and keep every receipt.

Retention is a portion of each payment that you hold back until the end of the defects period. The rate is agreed in your contract. Under many standard forms, half is released at practical completion and the rest once defects are put right (Designing Buildings), but always check what your own contract says.

How do you control variations once building starts?

Variations, changes to the agreed scope, are one of the biggest causes of overruns. They are not always avoidable, but they can be controlled:

  • Freeze the design before you start. Decide on room sizes, window positions and finishes during design, when changes cost only drawing time.
  • Put every change in writing. Ask for a written price and time effect, and approve it before the work is done.
  • Price changes on BQ rates. Where the BQ has a similar item, use its rate. This is one of the main reasons to have a priced BQ.
  • Keep a running total. Track approved variations against your contingency so there are no surprises in the final account.
  • Beware of "while you're at it". Small extras agreed verbally on site add up quickly.

How should you plan a contingency?

A contingency is a sum you set aside, separate from the contract sum, for genuinely unforeseen costs such as unexpected ground conditions. How much you need depends on how complete the design is, what is known about the soil, whether you are building on a sloping or rocky site, and how much of the price can change with material costs. A finished design with a detailed BQ needs a smaller reserve than an outline design.

Keep the contingency under your own control, not inside the contractor's price, and spend it only with written approval. If you need help estimating the overall budget, read our guide to the cost of building a house in Kenya.

What else keeps a build on budget?

  • Choose the right contractor. A registered, adequately funded firm is less likely to stall mid-project. Use our guides on how to choose a building contractor in Kenya and how to check if a contractor is NCA registered.
  • Get approvals first. Work stopped for missing permits or an unregistered project costs time and money, so complete county approvals and NCA project registration before work starts.
  • Agree a programme. A written schedule shows delays early, when they are cheaper to fix.
  • Check deliveries. Confirm materials delivered match the quantity and quality paid for.
  • Ask for regular progress reports with photos, work done, money spent and money committed.

How Msingi can help

Msingi Engineering Group (Msingi), the trading name of Msingi Africa Ltd, is an integrated engineering, design-build and property development company in Nairobi, registered with the National Construction Authority as a building works contractor with a current annual practising licence. Architecture, structural engineering and MEP are coordinated by one accountable team, so design decisions are made with build cost in mind.

Our approach is built around clear scopes and disciplined delivery to keep projects aligned with agreed costs, defined costs and realistic timelines, and direct, proactive progress updates. For predictable cost and delivery, our Family Typology homes are standard, fully engineered prototype homes for eighth-acre and quarter-acre plots. Talk to us about your project.

Frequently asked questions

What is a bill of quantities in Kenya?

A bill of quantities (BQ) is a document, usually prepared by a registered quantity surveyor, that lists every item of work in a building with its measured quantity, such as concrete, walling, roofing and finishes. Contractors price each line, so all bids cover the same scope. The priced BQ is then used to value payments, price variations and agree the final account.

Do I need a quantity surveyor to build a house in Kenya?

For most registered building projects, yes in practice: NCA project registration asks for a BQ summary signed and stamped by a quantity surveyor. Beyond that requirement, a QS registered with BORAQS helps you set a realistic budget, compare quotes on the same scope, value each payment before you release money and price any changes fairly. Ask for the QS's registration details before appointing them.

What is the most common cause of construction cost overruns?

Research on Kenyan projects points to several causes rather than one: rising material prices, design changes, client changes to finishes, under-estimated budgets and contractors running short of cash. Many of these start before construction, with an incomplete design or a quote that leaves items out. Finishing the design and getting a priced BQ reduces most of these risks.

Is a fixed-price contract better for avoiding overruns?

A fixed lump-sum contract can give more price certainty, because the contractor carries more of the risk of quantities and, depending on the terms, prices changing. It works best when the design is complete. If the design is unfinished, a lump sum may include a large risk allowance, and changes will still be priced as variations. Read the price adjustment clause carefully.

How much deposit should I pay a building contractor?

We are not aware of any fixed legal amount in Kenya; it is agreed in the contract. A sensible approach is a modest mobilisation advance tied to a signed contract, then pay in stages linked to completed, inspected work. Avoid paying large sums for work not yet done, pay only into the contracted company's account and keep receipts and payment certificates for every instalment.

What is retention money in construction?

Retention is a portion of each interim payment that the client holds back to make sure the contractor completes the work properly and fixes defects. The percentage is set in the contract. Often, part is released at practical completion and the rest at the end of the defects liability period, once the contractor has put right any faults.

How do I handle changes during construction without overspending?

Make every change a written variation. Ask the contractor for the cost and time effect first, approve it in writing, and price it using rates from the BQ where possible. Track approved variations against your contingency. Avoid agreeing extras verbally on site, because small changes add up and are hard to dispute later.