Building Plan Approval in Nairobi and Kenya: Permits, NCA, NEMA and County Steps

By Msingi Engineering Group Updated 9 min read

A completed two-storey family home with a first-floor balcony.

Building approval in Nairobi, and in every other Kenyan county, is not a single permit. It is a chain of approvals from different authorities, each with its own law, documents and timeline. Getting the order right, and knowing what each authority actually requires, is the difference between a project that starts on schedule and one that stalls or faces an enforcement notice. This guide explains the building permit process in Kenya step by step, with Nairobi-specific detail where it applies.

Key takeaways

  • County development permission is required by section 57 of the Physical and Land Use Planning Act, 2019; building without it is an offence carrying a fine of up to KSh 500,000, up to two months' imprisonment, or both.
  • The Act gives the county 30 days to decide on a compliant application, and treats permission as given if there is no written response within 60 days.
  • Architects reported an average of 13.1 weeks, and a range of 2 to 25 weeks, to obtain approval through Nairobi's online system in 2025.
  • The owner must register the project with the National Construction Authority (NCA) within 30 days of awarding the contract, and registration is currently free.
  • NEMA lists its environmental impact assessment licence fee at 0.1% of total project cost, with a minimum of KSh 10,000.

What approvals do you need to build a house in Kenya?

Most residential projects need the approvals below. Larger or special projects may also need others, such as Water Resources Authority (WRA) or Kenya Civil Aviation Authority (KCAA) clearances, which the NCA asks to see where they apply.

Approval Authority Legal basis When
Development permission (building plan approval) County government Physical and Land Use Planning Act, 2019, sections 57–61 Before any work starts
Environmental licence or decision National Environment Management Authority (NEMA) Environmental Management and Co-ordination Act and EIA regulations Before work starts; NEMA advises applying at least three months ahead
Project registration National Construction Authority (NCA) NCA Regulations 2014, regulation 17 Within 30 days of awarding the contract
Occupation certificate County government County development control rules After completion and final inspection

The design itself must follow the National Building Code 2024, published as Legal Notice No. 47 on 1 March 2024, which replaced the 1968 building by-laws.

How does building plan approval work in Nairobi?

The process is set by the Physical and Land Use Planning Act, 2019 and applies in every county. In Nairobi, applications are lodged online through the Nairobi Planning and Development Management System (NPDMS) by registered professionals.

  1. Prepare the drawings. Section 59 requires plans and documents to be prepared by qualified, registered and licensed professionals, who must be able to prove their credentials.
  2. Apply and pay. You apply in the prescribed form and pay the county's fees. If you are not the registered owner, you must include the owner's written consent.
  3. Public notice. The Act requires the applicant to notify the public of the proposed development and invites objections.
  4. Circulation. Within 7 days, the county sends the application to relevant agencies, such as roads, health, survey, utilities and environment, which have 14 days to comment.
  5. Decision. The county must grant (with conditions) or refuse a compliant application within 30 days, giving reasons in writing for a refusal.
  6. Appeal if needed. An aggrieved applicant may appeal to the County Physical and Land Use Planning Liaison Committee within 14 days; the committee must decide within 14 days, with a further appeal to the Environment and Land Court.

Nairobi adds its own layer. The Nairobi City County Development Control Policy 2026 introduces a one-time Development Impact Fee, calculated as gross floor area multiplied by a use-class factor and a location factor. It must be paid before a building permit is issued. The Star reported in July 2026 that the policy had been gazetted and was in force.

What documents do you need for building approval in Kenya?

Each county publishes its own checklist, so confirm it before you submit. The legal minimum under the Physical and Land Use Planning Act is the prescribed application form, the county fees, plans and particulars prepared by registered professionals, and the owner's written consent where the applicant is not the owner.

The NCA's list for project registration is a useful master checklist, because it brings together the outputs of the other approvals:

  • Approved architectural and structural drawings
  • County physical planning approvals (approval permits, letters or the PPA2 form)
  • NEMA approval and any other regulatory licences that apply
  • The bill of quantities (BQ) summary page, signed and stamped by the quantity surveyor
  • The developer's KRA PIN
  • The signed contract or agreement with the contractor
  • Supervision commitment letters from the consultants
  • Proof that the contractor, sub-contractors and consultants are registered and licensed for the current year

How long does building approval take in Nairobi?

The law and the reality differ. On paper, a compliant application should be decided within 30 days, and the Act deems permission granted if no written response arrives within 60 days. In practice, the Architectural Association of Kenya's Status of the Built Environment Report 2025 found that its members waited an average of 13.1 weeks for approval through Nairobi's NPDMS, with individual cases ranging from 2 to 25 weeks.

Stage Statutory or published period Source
County circulates application to agencies 7 days PLUPA 2019, s.60
Agencies comment 14 days PLUPA 2019, s.60
County decision on a compliant application 30 days PLUPA 2019, s.61
Deemed approval if no written response 60 days PLUPA 2019, s.58(6)
Actual Nairobi average, 2025 13.1 weeks (range 2–25 weeks) AAK 2025
NEMA screening of a summary project report 5 days NEMA
NEMA EIA licence 45–90 days NEMA
NCA evaluation after site due diligence 7 working days NCA

The AAK report also found that, as of 2025, only eight of Kenya's 47 counties had online permitting systems, and it recorded frequent downtime, limited information on application status and requests for unofficial "facilitation" payments. Build these realities into your programme; our guide to how long it takes to build a house in Kenya shows how approvals fit into the overall timeline.

Do you need a NEMA licence to build a house?

Most projects need an environmental decision from NEMA before work starts, either a licence or written confirmation that a fuller assessment is not required; what you submit depends on the project's risk category. For low- or medium-risk projects, NEMA requires a Summary Project Report prepared by a registered environmental impact assessment (EIA) expert, covering the project, its location and ownership, likely impacts, mitigation and evidence of public consultation. NEMA says these reports are submitted online and screened within five days. Larger developments need a fuller study.

NEMA's environmental licensing page lists the EIA licence fee as 0.1% of total project cost, with a minimum of KSh 10,000, states that licences are issued within 45 to 90 days, and advises applying at least three months before you start. Lenders check this too: KCB's construction mortgage asks for NEMA approval of the EIA or an exemption letter.

How does NCA project registration work?

Regulation 17 of the NCA Regulations 2014 requires every construction project, public or private, to be registered with the National Construction Authority. The NCA is clear that registration is the developer's responsibility, not the contractor's, and that the application is due within 30 days of awarding the contract. You apply through the NCA project registration portal or at a regional office.

Registration is currently free. According to the NCA's FAQs, evaluation takes about seven working days after an on-site due diligence visit. The contractor you appoint must be NCA registered with a valid practising licence; see our guide on how to check if a contractor is NCA registered.

What happens if you build without approval in Kenya?

The penalties are set out in the Physical and Land Use Planning Act, 2019:

  • Building without permission (section 57): a fine of up to KSh 500,000, imprisonment of up to two months, or both. The county can also order the land restored to its original condition within 90 days and recover the cost if you fail to do it.
  • Building differently from the approved plans (section 67): a fine of not less than KSh 1 million, imprisonment of not less than five years, or both. If you need a material change, apply for a fresh permission first.
  • Letting permission lapse (section 64): permission expires if building has not started within three years, though the county may extend it by one year.

Unapproved buildings also cause practical problems: lenders such as KCB ask for approved plans before releasing construction finance, and in Nairobi the Development Control Policy 2026 ties the occupation certificate to payment of the Development Impact Fee and to repairing any public infrastructure damaged during construction. Confirm your specific obligations with your architect, planner or advocate.

How Msingi can help

Msingi Engineering Group (Msingi) is an integrated engineering, design-build and property development company in Nairobi, registered with the National Construction Authority (NCA) as a building works contractor with a current annual practising licence. Because architecture, structural engineering and MEP (mechanical, electrical and plumbing) are coordinated by one accountable team, the drawings, the bill of quantities and the documents each authority asks for are prepared together and stay consistent.

Msingi has delivered more than 20 projects, from family homes in Thome, Karen and Tatu City to civil works and building services for the Zipline KE-1 distribution centre in Kisumu County. You can review the firm's credentials and its building works. For the full process from land to handover, read how to build a house in Kenya, or start a conversation at Build with Msingi.

Frequently asked questions

How long does it take to get building plans approved in Nairobi?

The Physical and Land Use Planning Act, 2019 gives the county 30 days to decide on a compliant application, and deems approval given if there is no written response within 60 days. In practice, the Architectural Association of Kenya found its members waited an average of 13.1 weeks for Nairobi approvals in 2025, ranging from 2 to 25 weeks.

Who is responsible for registering a project with the NCA?

The developer, meaning the property owner. The National Construction Authority states that project registration is the developer's responsibility, not the contractor's, whether the project is commercial or private. The NCA Regulations 2014 require the application within 30 days of awarding the contract. Registration is currently free and can be done online or at an NCA regional office.

How much does a NEMA licence cost for a house?

NEMA's environmental licensing page lists the environmental impact assessment licence fee as 0.1% of the total project cost, with a minimum of KSh 10,000. You will also pay the registered EIA expert who prepares the report. Fee schedules change, so confirm the current amount with NEMA or your EIA expert before applying.

What happens if the county does not respond to my building application?

Under section 58(6) of the Physical and Land Use Planning Act, 2019, if you receive no written response within 60 days of applying, development permission is assumed to have been given. Professionals still advise keeping full records of the submission and any correspondence. Ask your architect or advocate to confirm your position before relying on deemed approval.

Can I change my house design after approval?

Yes, but apply first. Building work that is inconsistent with the approved plans is an offence under section 67 of the Physical and Land Use Planning Act, 2019, carrying a fine of not less than KSh 1 million, imprisonment of not less than five years, or both. The Act allows you to apply for permission for material variations before you build them.

How long is a building approval valid in Kenya?

Development permission lapses if the project has not started within three years of the permission being granted, under section 64 of the Physical and Land Use Planning Act, 2019. The county may extend it by one year on application and can add conditions. The Act also allows counties to impose conditions or fines if building works are not completed within five years.

Is there a Development Impact Fee in Nairobi?

Yes. Nairobi's Development Control Policy 2026 introduces a one-time Development Impact Fee charged at the building permit stage. It is calculated from gross floor area, a use-class factor and a location factor, and must be paid before a building permit is issued. The occupation certificate is also withheld until the fee is fully paid.